Trying to get caught up on posting the progress -- sorry to all of you who have been bugging me for more pictures.
The skylights have been installed in both the kitchen and the living room. Three in each with opening ones in the kitchen for ventilation. All of the reclaimed styrofoam insulation has been installed in the stud walls which allows us to really see how the rooms will look.
The last of the shed walls have been framed up which means now we actually have to use the doorways to enter and exit the house. We've got a small crew working on the rest of the straw work. They'll be filling in the gaps with slip straw next week and hopefully will start plastering before the end of the month.